DAVIDSON COUNTY I-24

The grading, drainage, construction of a retaining wall, signal traffic and paving on I-24 at the EB exit ramp to SR 254 (Bell Rd., Exit 59) (LM 23.25 - LM 24.30)

· Nightly, excluding weekends, 8 p.m. – 5 a.m., There will be lane closures on I-24 EB and Bell Road, for construction activities.

· 11/12 5 a.m. continuously until 11/13, 5 p.m., the I-24 EB exit ramp to Bell Road (Exit 59) will be closed to place epoxy overlay.

The random on-call signing on various Interstate and State Routes.

· MM 54 – 53, 11/14 – 11/16, 8 p.m. – 5 a.m., There will be a double right lane closure on I-24 WB for graffiti removal

DAVIDSON / RUTHERFORD COUNTY, I-24

The construction of an Intelligent Transportation System and upgrades from Nashville to Murfreesboro (Phase 2)

· 11/10, 8 p.m. – 5 a.m., There will be alternating lane closures and rolling road blocks for the installation of overhead sign gantries.

RUTHERFORD COUNTY, I-24

The resurfacing on I-24 from E of Medical Center Pkwy to Stones River Bridge (MM 76 – 80)

· Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures EB and WB for installation of pavement markings.

The resurfacing on I-24 from E of Epps Mill Road through Bedford County to the Coffee County Line.

· Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures EB and WB for paving activities.

DAVIDSON COUNTY I-40

The grading,drainage, signals, and paving on I-40 at the U.S. 70 (S.R. 24, Charlotte Pike) westbound exit ramp (L.M. 9.65)

· 11/10, 8 p.m. – 5 a.m., There will be a lane closure on the I-40 westbound off ramp to Charlotte Pk (Exit 201) for attenuator and ROW fence install.

The resurfacing on I-40 from near U.S. 70 (S.R. 24) (L.M. 9.61) to near 46th Avenue (L.M. 13.33).

· Nightly, 8p.m. – 5 a.m., There will be alternating lane closures in both directions on I-40 from Charlotte Pk to 46th Ave for paving, striping, and deck seal repair. (MM 201-204)

The grading, drainage, construction of bridges, retaining walls and paving on I-40 (MM 216) at the Donelson Pike interchange

· Daily, 10 a.m. – 2 p.m., There will be rolling roadblocks for blasting operations. Blasts are tentatively scheduled for 11/10, 11/14, 11/16

The random on-call signing on various Interstate and State Routes.

· MM 209-207, 11/14-11/16, 8 p.m. – 5 a.m., There will be a single left lane closure on I-40 WB for graffiti removal

· MM215-214, 11/14 - 11/16, 8 p.m. – 5 a.m., There will be a single left lane closure on I-40 WB for graffiti removal

DAVIDSON COUNTY I-440

The random on-call signing on various Interstate and State Routes.

· MM 6-7, 11/14 – 11/16,8 P.M. – 5 A.M., There will be a Single right lane closure on I-440 EB for graffiti removal

· MM 0-1, 11/14-11/16, 8 p.m. – 5 a.m., There will be alternating single right and single left lane closure on I-440 WB for graffiti removal

DICKSON / WILLIAMSON / CHEATHAM / DAVIDSON COUNTIES

The expansion of the SmartWay Intelligent Transportation System (ITS) on I-40 from near I-840 in Dickson County to near U.S. 70S (Exit 196) in Davidson County

· Daily, 7:30 a.m. – 6 p.m., There will be temporary daytime shoulder closure for the drilling of the foundations for CCTV cameras at various locations throughout the project limits.

WILSON COUNTY I-40

The resurfacing on I-40 from South Hartman to the Smith County Line

· Nightly, 8 p.m. - 5 a.m., There will be alternating lane closures on I-40 EB and WB from S. Hartman to Smith Co. Line for final pavement marking and shoulder stone.

DAVIDSON COUNTY I-65

The installation of an overhead sign structure on I-65

· LOOK AHEAD, 11/20, 4:30 a.m. – 11 a.m., There will be a double right lane closure and rolling road blocks on I-65 SB/I-24 EB, near exit 87 (W. Trinity Lane), to install overhead sign structure.

· Daily, 9 a.m. – 3 p.m., There will be left and right shoulder closures on I-65 SB for overhead sign footing installation, installation of overhead sign and clean up. MM 86.8

DAVIDSON COUNTY, I-65 & SR 245

The grading, drainage, construction of a retaining wall, signals and paving on I-65 at the NB exit ramp to SR 254 (OHB, Exit 74A)

· Daily, 9 a.m. – 3 p.m. There will be temporary lane closures on SR 254(OHB) in both directions for grading and signal work. Two lanes will remain open in each direction.

MAURY COUNTY, I-65

I65 interchange improvements at SR99 including grading, paving, drainage, signal, light retaining walls.

· 11/10 – 11/11, 8 p.m. – 5 a.m., There will be temporary lane closures on I 65 SB in both lanes shifting traffic over the Phase 2 bridge. At least one lane will remain open in each direction.. (MM 47 – 46)

MARSAHLL COUNTY, I-65

The resurfacing on I-65 from North of US 31A (SR 11) (LM 0.38) to the Maury County line MM 22-35

· Nightly, 7 p.m. – 6 a.m., There will be nighttime lane closures both NB and SB for resurfacing activities. One lane to remain open at all times.

ROBERTSON COUNTY I-65

Grading, drainage, construction of bridges and retaining walls, ITS and paving

· Nightly, 8 p.m. – 4 a.m., There will be temporary lane closures on I-65 NB and SB for roadway maintenance and preparation for traffic shifts on north side of project, one lane will remain open at all times.

WILLIAMSON COUNTY, I-65

I-65 Interchange at Buckner Road

· 11/14 – 11/16, 8 p.m. – 5 a.m., There will be a lane closure on I-65 NB from MM 55.40 to MM 56.00 for barrier rail installation.

DAVIDSON COUNTY SR 1

SR-1 (Broadway) Bridge over CSX and 11th Ave

· Nightly, 8 p.m. – 5 a.m., There will be a lane closure on SR-1 WB on the corner of 10th St and Broadway to retire a gas service line.

DAVIDSON COUNTY SR 6

The resurfacing on U.S. 31E (S.R. 6) from north of S.R. 45 (Old Hickory Boulevard) (L.M. 18.60) to the Sumner County line (L.M. 22.87)

· Nightly, 8 p.m. – 5 a.m., There will be a lane closure for paving operations.

MAURY COUNTY SR 6

Resurfacing on US31 (SR6) including epoxy overlay

· 11/10 – 11/11, 8 p.m. – 5 a.m., There will be temporary lane closures on SR 6 both directions from the Williamson County Line to Crossing Blvd for pavement markings, striping and curb ramp work

DAVIDSON COUNTY SR 65

The resurfacing on U.S. 431 (S.R. 65) from U.S. 41 (S.R. 11, Dickerson Pike) to south of Seymour Hollow Road.

· Daily, 9 A.M. – 3 P.M., There will be a lane closure on Whites Creek Pk from Lloyd Rd to Seymour Hollow Rd for milling.

· Nightly, 8 p.m. – 5 a.m., There will be a lane closure on Trinity Ln from Dickerson Pk to Whites Creek Pk for concrete curb ramp work.

DAVIDSON COUNTY, SR 112

SR 112 (US 41A/Clarksville Pike) from SR 12 (Ashland City Highway) to SR 155 (Briley Pkwy.) - Piedmont Move Prior

· Daily, 9 a.m. – 3 p.m. There will be a temporary alternating lane closure on SR 112 Clarksville Pike in both directions for grade work, storm drainage, sanitary sewer and overhead power. Flaggers will be utilized.

DAVIDSON COUNTY SR 155

The resurfacing on S.R. 155 (Briley Pkwy) from the McGavock Pike ramp to the bridge over I-65 including S.R. 6 from Ellington Pkwy (L.M.15.49) to Gallatin Pike (L.M. 16.49)

· Nightly (excluding Saturday), 8 p.m. – 5 a.m., There will be temporary lane closures, in both directions on Briley Parkway (SR 155) for final striping and rumble strip installation. Temporary ramp closures may be needed also.

MONTGOMERY COUNTY SR 13

Consisting of: the grading, drainage, construction of welded steel plate girder bridge, retaining wall and paving on S.R. 149 and S.R. 13 from River Road to Zinc Plant Road. MM 17-19

· Daily, 9 a.m. – 3 p.m.., There will be periodic single-lane traffic flow and flagging operations along SR-13 from 9AM to 3PM, therefore delays are expected. Traffic will be swapped early November to its final alignment. Mayhew Road expected to be open early November.

MONTGOMERY COUNTY US 41A / SR 12

Bicycles and Pedestrian Facilities

· Daily, 9 a.m. – 3 p.m., Sidewalk construction. Contractor to utilize 1 lane of traffic for clean up and punch list items.

MONTGOMERY COUNTY, SR 13, SR 48 & SR112

Milling and Paving Operations on SR 13 (Wilma Rudolph Blvd) SR 48 (College St.) and SR 112 (North 2nd/University Ave.)

· Nightly, 8 p.m. – 5 a.m., There will be lane closures for milling and paving operations.

RUTHERFORD COUNTY SR 1

LPLM: Town of Smyrna Street Scapes on SR-1

· Daily, 9 a.m. – 3 p.m., There will be alternating lane closures for construction activities.

RUTHERFORD COUNTY SR 99

The grading, drainage, construction of retaining walls, signals and paving on SR-99 (New Salem Hwy) from near I-24 to SR-96 (Old Fort Pkwy)

· Daily, 9 a.m. – 3 p.m., There will be periodic flagging operations for construction activities.

The resurfacing of SR-99 from Veterans Pkwy to Cason Lane

· Daily, 8:30 a.m. – 2:30 p.m., There will be flagging operations for resurfacing activities.

RUTHERFORD COUNTY 266

The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR-266 (Jefferson Pike) from SR-102 (LM 5.0) to E. of I-840 (LM 9).

· Daily, 9 a.m. – 3 p.m., There will be periodic flagging operations for construction activities.

SUMNER COUNTY SR 6

Potholing/Excavation for underground conduit

· Daily, 9 a.m. – 3 p.m., Temporary daytime lane and shoulder closure at Lock 4 Road

WILLIAMSON COUNTY SR 6

Grading, drainage and paving work on SR 6 (Franklin Road) from south of Moore's Lane (LM 15.93) to Concord Road (18.53) – (mm 15.93 – 18.53)

· Daily 9 a.m. – 3 p.m., We anticipate needing intermittent stoppages of traffic, and/or temporary lane closures (one direction at a time) between the hours of 9AM and 3PM Monday thru Friday, and possibly on Saturday (although not currently scheduled) for various construction activity including paving and utility work throughout the project.

We are planning on having extended delays and possible lane closures for construction activities for the following side roads: Ashby, Drive, Holly Tree Gap Rd, Long St, West Concord, Wikle Rd and Mt. View Rd.

WILLIAMSON COUNTY SR 96

Grading, drainage, construction of bridges and signals on SR 96 from east of Arno Rd (LM 14.72) to SR 252 (Wilson Pk) (LM 20.62).

· Daily, 9 a.m. – 3 p.m., There will be lane closures and brief stoppages of traffic for utility relocations and grading work.

The resurfacing on SR-96 from near Boyd Mill Ave (L.M. 7.86) to Edward Curd Ln (L.M. 13.29).

· Nightly, 8 p.m. – 5 a.m., (Excluding Friday and Saturday) There will be a lane closure between Main St and I-65 for paving and striping operations.

· Nightly, 9 a.m. – 9 p.m., (Excluding Friday and Saturday) There will be a lane closure between Boyd Mill Ave and Hillsboro Rd (SR-106/US-431) for paving and striping operations.

WILLIAMSON COUNTY SR 100

The resurfacing of SR100 from Deer Ridge Rd (LM 3.00) to Fernvale Rd. (LM 6.85).

· Daily, 9 a.m. – 2:30 p.m., There will be a lane closure for final striping.

WILLIAMSON COUNTY SR 106

I-65 Interchange at Buckner Road

· 11/10 – 11/11, 9 a.m. – 3 p.m., & 11/14 – 11/16, 9 a.m. – 3 p.m., There will be one lane flagging operations on Lewisburg Pike (SR 106) from LM 3.2 to LM 3.2 for box culvert construction.

The replacement of a 60" corrugated metal pipe on US 431 (SR 106) at LM 13.65

· 11/15 – 11/16 9 a.m. continuously until 3 p.m. 11/16, There will be a full road closure on SR 106 (Lewisburg Pk) between Carnton Ln. and Eastern Flank Cir. for reshaping of culvert outlet. Traffic will be detoured via SR 6 (Columbia Ave) and SR 397 (Mack Hatcher Pkwy). Detour signs will be in place.

>> MAINTENANCE & UTILITIES

DAVIDSON COUNTY I-24

Milling and Paving

· Nightly, 8 p.m. – 5 a.m., Alternating lane closures on EB lanes at MM53 – 63.

DAVIDSON COUNTY I-40

Milling and Paving

· 11/15, 7 P.M. – 5 A.M., Lane closures for milling and paving operations at MM 192

DAVIDSON COUNTY I-65,

Installing underground utilities

· 11/10, 10 a.m. – 10:30 a.m., Rolling roadblock NB from Briley Pkwy to Trinity Ln. for blasting operations off TDOT right of way to avoid debris

GILES COUNTY I-65

Repairing hole in bridge deck

· 11/15, 9 a.m., - 3 p.m., There will be various lanes closures NB. No more than one lane per direction at a time. Will maintain one lane of travel traffic in each direction

DAVIDSON COUNTY I-24The grading, drainage, construction of a retaining wall, signal traffic and paving on I-24 at the EB exit ramp to SR 254 (Bell Rd., Exit 59) (LM 23.25 - LM 24.30)Nightly, excluding weekends, 8 p.m. – 5 a.m., 11/12 5 a.m. continuously until 11/13, 5 p.m., The random on-call signing on various Interstate and State Routes.MM 54 – 53, 11/14 – 11/16, 8 p.m. – 5 a.m., DAVIDSON / RUTHERFORD COUNTY, I-24The construction of an Intelligent Transportation System and upgrades from Nashville to Murfreesboro (Phase 2)11/10, 8 p.m. – 5 a.m., RUTHERFORD COUNTY, I-24The resurfacing on I-24 from E of Medical Center Pkwy to Stones River Bridge (MM 76 – 80)Nightly, 8 p.m. – 5 a.m., The resurfacing on I-24 from E of Epps Mill Road through Bedford County to the Coffee County Line.Nightly, 8 p.m. – 5 a.m., DAVIDSON COUNTY I-40The grading,drainage, signals, and paving on I-40 at the U.S. 70 (S.R. 24, Charlotte Pike) westbound exit ramp (L.M. 9.65)11/10, 8 p.m. – 5 a.m., The resurfacing on I-40 from near U.S. 70 (S.R. 24) (L.M. 9.61) to near 46th Avenue (L.M. 13.33).Nightly, 8p.m. – 5 a.m., The grading, drainage, construction of bridges, retaining walls and paving on I-40 (MM 216) at the Donelson Pike interchangeDaily, 10 a.m. – 2 p.m., The random on-call signing on various Interstate and State Routes.MM 209-207, 11/14-11/16, 8 p.m. – 5 a.m., MM215-214, 11/14 - 11/16, 8 p.m. – 5 a.m., DAVIDSON COUNTY I-440The random on-call signing on various Interstate and State Routes.MM 6-7, 11/14 – 11/16,8 P.M. – 5 A.M., MM 0-1, 11/14-11/16, 8 p.m. – 5 a.m., DICKSON / WILLIAMSON / CHEATHAM / DAVIDSON COUNTIESThe expansion of the SmartWay Intelligent Transportation System (ITS) on I-40 from near I-840 in Dickson County to near U.S. 70S (Exit 196) in Davidson CountyDaily, 7:30 a.m. – 6 p.m., WILSON COUNTY I-40The resurfacing on I-40 from South Hartman to the Smith County LineNightly, 8 p.m. - 5 a.m., DAVIDSON COUNTY I-65The installation of an overhead sign structure on I-65LOOK AHEAD, 11/20, 4:30 a.m. – 11 a.m., Daily, 9 a.m. – 3 p.m., DAVIDSON COUNTY, I-65 & SR 245The grading, drainage, construction of a retaining wall, signals and paving on I-65 at the NB exit ramp to SR 254 (OHB, Exit 74A)Daily, 9 a.m. – 3 p.m. MAURY COUNTY, I-65I65 interchange improvements at SR99 including grading, paving, drainage, signal, light retaining walls.11/10 – 11/11, 8 p.m. – 5 a.m., MARSAHLL COUNTY, I-65The resurfacing on I-65 from North of US 31A (SR 11) (LM 0.38) to the Maury County line MM 22-35Nightly, 7 p.m. – 6 a.m., ROBERTSON COUNTY I-65Grading, drainage, construction of bridges and retaining walls, ITS and pavingNightly, 8 p.m. – 4 a.m., WILLIAMSON COUNTY, I-65I-65 Interchange at Buckner Road11/14 – 11/16, 8 p.m. – 5 a.m., DAVIDSON COUNTY SR 1SR-1 (Broadway) Bridge over CSX and 11th AveNightly, 8 p.m. – 5 a.m.,DAVIDSON COUNTY SR 6The resurfacing on U.S. 31E (S.R. 6) from north of S.R. 45 (Old Hickory Boulevard) (L.M. 18.60) to the Sumner County line (L.M. 22.87)Nightly, 8 p.m. – 5 a.m., MAURY COUNTY SR 6Resurfacing on US31 (SR6) including epoxy overlay11/10 – 11/11, 8 p.m. – 5 a.m., DAVIDSON COUNTY SR 65The resurfacing on U.S. 431 (S.R. 65) from U.S. 41 (S.R. 11, Dickerson Pike) to south of Seymour Hollow Road.Daily, 9 A.M. – 3 P.M., Nightly, 8 p.m. – 5 a.m., DAVIDSON COUNTY, SR 112SR 112 (US 41A/Clarksville Pike) from SR 12 (Ashland City Highway) to SR 155 (Briley Pkwy.) - Piedmont Move PriorDaily, 9 a.m. – 3 p.m. DAVIDSON COUNTY SR 155The resurfacing on S.R. 155 (Briley Pkwy) from the McGavock Pike ramp to the bridge over I-65 including S.R. 6 from Ellington Pkwy (L.M.15.49) to Gallatin Pike (L.M. 16.49)Nightly (excluding Saturday), 8 p.m. – 5 a.m., MONTGOMERY COUNTY SR 13Consisting of: the grading, drainage, construction of welded steel plate girder bridge, retaining wall and paving on S.R. 149 and S.R. 13 from River Road to Zinc Plant Road. MM 17-19Daily, 9 a.m. – 3 p.m.., MONTGOMERY COUNTY US 41A / SR 12Bicycles and Pedestrian FacilitiesDaily, 9 a.m. – 3 p.m., MONTGOMERY COUNTY, SR 13, SR 48 & SR112Milling and Paving Operations on SR 13 (Wilma Rudolph Blvd) SR 48 (College St.) and SR 112 (North 2nd/University Ave.)Nightly, 8 p.m. – 5 a.m., RUTHERFORD COUNTY SR 1LPLM: Town of Smyrna Street Scapes on SR-1Daily, 9 a.m. – 3 p.m., RUTHERFORD COUNTY SR 99The grading, drainage, construction of retaining walls, signals and paving on SR-99 (New Salem Hwy) from near I-24 to SR-96 (Old Fort Pkwy)Daily, 9 a.m. – 3 p.m.,The resurfacing of SR-99 from Veterans Pkwy to Cason LaneDaily, 8:30 a.m. – 2:30 p.m., RUTHERFORD COUNTY 266The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR-266 (Jefferson Pike) from SR-102 (LM 5.0) to E. of I-840 (LM 9).Daily, 9 a.m. – 3 p.m., SUMNER COUNTY SR 6Potholing/Excavation for underground conduitDaily, 9 a.m. – 3 p.m., WILLIAMSON COUNTY SR 6Grading, drainage and paving work on SR 6 (Franklin Road) from south of Moore's Lane (LM 15.93) to Concord Road (18.53) – (mm 15.93 – 18.53)Daily 9 a.m. – 3 p.m., WILLIAMSON COUNTY SR 96Grading, drainage, construction of bridges and signals on SR 96 from east of Arno Rd (LM 14.72) to SR 252 (Wilson Pk) (LM 20.62).Daily, 9 a.m. – 3 p.mThe resurfacing on SR-96 from near Boyd Mill Ave (L.M. 7.86) to Edward Curd Ln (L.M. 13.29).Nightly, 8 p.m. – 5 a.m., (Excluding Friday and Saturday) Nightly, 9 a.m. – 9 p.m., (Excluding Friday and Saturday) WILLIAMSON COUNTY SR 100The resurfacing of SR100 from Deer Ridge Rd (LM 3.00) to Fernvale Rd. (LM 6.85).Daily, 9 a.m. – 2:30 p.m., WILLIAMSON COUNTY SR 106I-65 Interchange at Buckner Road11/10 – 11/11, 9 a.m. – 3 p.m., & 11/14 – 11/16, 9 a.m. – 3 p.m., .The replacement of a 60" corrugated metal pipe on US 431 (SR 106) at LM 13.6511/15 – 11/16 9 a.m. continuously until 3 p.m. 11/16, >> MAINTENANCE & UTILITIESDAVIDSON COUNTY I-24Milling and PavingNightly, 8 p.m. – 5 a.m., DAVIDSON COUNTY I-40Milling and PavingDAVIDSON COUNTY I-65,Installing underground utilities11/10, 10 a.m. – 10:30 a.m.,GILES COUNTY I-65Repairing hole in bridge deck11/15, 9 a.m., - 3 p.m., There